A. Capacity Enhancement of Sponge iron plant from 2, 16, 000 TPA to 2, 73, 900 TPA by change in raw material mix; AND Capacity Enhancement of CPP (AFBC) from Existing 24 MW to 37 MW by i. Replacement of indigenous coal with imported coal ii. Modification in existing boiler and Turbine with additional new Turbine; AND Capacity Enhancement of power plant (WHRB) from 14MW to22MW; AND Capacity expansion of Ferro-alloy unit to manufacture 36,000 TPA to 85,200 TPA Ferro Alloys by Installing I x 18 MVA and 4 X 1.5 MVA Submerged Arc Furnacel AND Installation of66,000 TPA Sinter plant and 16500 TPA Briquette plant
1.
Summary EIA Report in English Language
2.
Summary EIA Report in Hindi Language
|
The copies of Summary
EIA Report (English & Hindi) and Draft EIA Report
are available for inspection for public at the offices of
following authorities during normal office hours till the date
of public hearing |
S. No. |
Authority |
Address |
01 |
Director |
Ministry of Environment, Forest & Climate Change Indira Paryavaran Bhavan Jor Bagh Road New Delhi - 110 003 |
02 |
Chief Conservator of Forest |
Scientist D Joint Regional Office MOEFCC Aranyabhavan North Block Sec-19 Nava Raipur Atal Nagar Dist-Raipur. |
03 |
Collector |
Office
of the Collector, District-Raipur(C.G.). |
04 |
Chief Executive Officer |
Office
of the Zila Panchayat, District-Raipur (C.G.). |
05 |
Chief General Manager |
District Industries and Trade Center, District-Raipur (C.G.). |
06 |
Sarpanch/Secretary |
Office
of the Gram Panchayat Siltara Tehsil & District-Raipur (C.G.). |
07 |
Member Secretary |
Chhattisgarh Environment Conservation Board, Paryavas Bhavan, North Block Sector-19, Nava Raipur Atak Nagar District-Raipur (C.G.) 492002 |
08 |
Regional Officer |
Regional Office, Chhattisgarh Environment Conservation
Board, Raipur(C.G.). |
|
The
interested persons may send their comments to the Regional
Office, Chhattisgarh
Environment Conservation Board at the Regional Office,
Chhattisgarh Environment Conservation Board, Raipur (C.G.)
|
Date of Public Hearing |
19/05/2022, Thursday |
Time of Public Hearing |
10:30 AM |
Venue of Public Hearing |
Premises CSIDC building, Industrial area phase-2 Distt-Raipur |
Status |
|
|
| | |